First half of March

We haven’t had lighting in the family room in two months, but I finally have a plan and LED bulbs so it’s time to put those in. It’s starting to look slightly more like a place someone would live in.



Also we have insulation for the first time in what seems like forever. This is another thing that we really needed a month or more earlier but all you can do is get on someone’s calendar and wait patiently. After the insulation was sprayed in the flooring arrived! The long pieces are over 10 feet long. I could carry only two bundles at a time.




I can’t put it in though until the joists are complete so that became a high priority. These are the ones installed with the addition but they were far enough away from the rot to be reusable. I sistered in new wood to make them stronger. At this point we were working towards having drywall again. Sometimes it helps to prioritize.

 